Skip to content

Case study · Metal casting

Unplanned downtime at a casting plant fell from 30 to 1.5 hours a month

PT Asian Isuzu Casting Center put condition monitoring on the motors, gearboxes, pumps, and blowers that cannot stop in the middle of a pour. Bearing anomalies now show up 4 to 6 weeks before the vibration can be felt, so repairs are scheduled for the off shift.

Results over 12 months

unplanned downtime per month

30 to 1.5 h

unplanned downtime per month

earlier warning on bearing anomalies

4 to 6 weeks

earlier warning on bearing anomalies

potential major failures repaired on schedule

6 jobs

potential major failures repaired on schedule

to pay back the investment

± 17 working days

to pay back the investment

The downtime hours and the Rp 20 million per hour loss are AICC’s figures. The avoided loss is simple arithmetic: 28.5 hours a month times Rp 20 million, about Rp 570 million a month, against Rp 450 million invested in sensors, panels, integration, and field work.

The challenge

Casting depends on drive motors, gearboxes, pumps, and blowers that run continuously. When one stops without warning, the mould flow stops with it, and the line cannot wait.

Maintenance used to be reactive. A failure was found when the machine had already stopped, adding up to about 30 hours of unplanned downtime a month. At roughly Rp 20 million an hour, hundreds of millions of rupiah were lost every month before a repair even began.

What we installed

Sensors went into six areas: Sand Tank 1 and 2, BE, MM, OC, and moulding pressure. All data stays on the plant’s local network and never goes out to the internet.

  • Vibration: Banner QM30VT2 on bearings and motors, read through a DXM over Modbus TCP
  • Temperature and pressure: Pt100 and pressure transmitters through an ifm IO-Link master
  • Current: clamp-on CTs, including on 3 kV motors, through a Mitsubishi FX5 PLC
  • An on-premise server in the plant, with no change to machine control logic

How the team uses it

Each sensor is compared with its own machine’s baseline and with the ISO 10816 zone limits. When a bearing’s vibration starts to climb, the maintenance team looks at the trend, confirms it against other parameters on the same machine, and schedules the repair.

Spectrum analysis catches early bearing raceway damage 4 to 6 weeks before the vibration can be felt or the bearing runs hot. That is enough time to get the parts ready and pick an off shift, without cutting into the casting schedule.

The result

Over 12 months, unplanned downtime fell from about 30 to 1.5 hours a month. Six potential major failures were handled as scheduled repairs on the off shift instead of as emergencies.

The system does not guarantee that a machine never fails. What changed is the timing: the signs show up earlier, so the team decides when a machine stops, not the machine.

On site

PT Asian Isuzu Casting Center

A vibration sensor mounted on top of a drive motor in the Sand Tank area at PT Asian Isuzu Casting Center
A vibration sensor on a drive motor in AICC’s Sand Tank area.
A green clamp-on CT around a motor cable inside an electrical panel at PT Asian Isuzu Casting Center
A clamp-on CT reading motor current in an AICC panel.
Presenting the Digital Andon dashboard on a large screen on the plant floor at PT Asian Isuzu Casting Center
Presenting Digital Andon on the AICC plant floor.

Start with the machines that cost most when they stop

AICC started with the assets in its most critical areas. We can work out with your team which machines are worth watching first, using your plant’s own figures.

  • No obligation to buy
  • A reply within business hours
  • WhatsApp works too